The conclusion of the inspection on the management of electricity supply of (EVN) in the 2021-2023 period announced by the MOIT on July 12 clearly shows the reasons why 85 wind power projects, transition solar power has been slow to put into operation and generate electricity.
Therefore, these projects have many legal procedures that need to be completed related to EVN such as: connection agreement; complete execution of the test; review test results; relevant regulations; procedures for energizing projects.
However, EVN has been slow in directing, operating and urging its member units to coordinate with investors of transitional wind and solar power projects to complete legal procedures related to EVN to put these projects into operation under the direction of MOIT.